Electricity projects set to boost Uganda

By DAVID BLAIR/XIAO XIANGYI | China Daily | Updated: 2018-09-05 08:00
Share
Share - WeChat
Ugandan employees of China International Water & Electric Corp in front of the switchyard of Isimba hydropower station. The project site is about 21km from Kayunga Town. Photo by Xiao Xiangyi / China Daily

East African country sees low-cost power from two dams being built on Nile as key to attracting investors, factories

By almost doubling Uganda's electricity generation capacity, two new dams on the Nile River, scheduled to begin operations within two years, will help transform the business attractiveness of the country.

The Isimba Dam, which is being built by China International Water & Electric Corp, will generate 183 megawatts every year. And the Karuma Dam, being built by Sinohydro, will generate 600 mW a year. Uganda now has total electricity generation capacity of about 810 mW.

Uganda has the highest electricity prices in East Africa, with a tariff, or price, of 15.3 US cents per kilowatt-hour in 2016. Kenya was at 15 US cents, Tanzania at 9.8 cents and Ethiopia at 2.4 cents per kWh, according to statista.com. In addition, Uganda's electricity prices have been rising 22 percent per year in the past three years, according to The Independent, a newsmagazine published in Kampala, Uganda.

"If this situation continues, then local companies, which produce goods that are at the same time imported into the country cheaply, are likely to become uncompetitive and possibly forced to shut down," Martin Kyeyune, the finance and economic adviser at Roofings Group, Uganda's leading producer of steel products, told The Independent.

Only 27 percent of the population has access to electricity and only 8 percent of rural villages have access, according to energypedia. Businesses are reluctant to locate in the country if they cannot get power.

Li Xiaogang, the authorized representative of Sinohydro in East Africa, says the Ugandan government is pushing for low-cost power and better transportation to promote the country's development.

"Hydropower always can provide cheap power, at 2 or 3 cents per kilowatt-hour. After Karuma and Isimba activate, they will dramatically decrease the tariff to 5 or 6 cents. This will attract a large number of companies and investors to operate their factories here," says Li.

He says the dams are very good projects for Uganda. He calculates that the Karuma Dam "will generate 4 billion kilowatt-hours at a price of about 5 cents per kilowatt-hour. It will bring the government of Uganda $200 million per year, almost 1 percent of GDP. The total investment is $1.6 billion, so in seven to 10 years, the Ugandan government will recoup its investment."

Li says the Karuma Dam cost $1.5 billion, of which 85 percent was funded by the Export-Import Bank of China and 15 percent by the government of Uganda, with a sovereign guarantee.

Of the 85 percent funded by the China Exim Bank, 55 percent is at concessional rates of interest, and 45 percent at market rates. The interest rate for the concessional loan is 2 percent, while the market rate loan is at 4 percent, he says.

1 2 Next   >>|
Most Viewed in 24 Hours
Top
BACK TO THE TOP
English
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
主站蜘蛛池模板: 瑞安市| 汤原县| 舒兰市| 云南省| 蓬溪县| 怀远县| 庆阳市| 德州市| 凤山县| 喀什市| 侯马市| 济宁市| 安徽省| 铁岭市| 吐鲁番市| 龙南县| 榕江县| 尚义县| 丰城市| 咸宁市| 汽车| 右玉县| 绥化市| 南郑县| 盐山县| 鹤山市| 德惠市| 柳江县| 呈贡县| 如东县| 从化市| 奉贤区| 万宁市| 黄平县| 白山市| 余干县| 永城市| 广州市| 山东省| 田东县| 田林县| 女性| 金昌市| 莱阳市| 抚州市| 文登市| 潼南县| 探索| 阿尔山市| 周宁县| 岳阳市| 新建县| 龙南县| 丽水市| 木里| 昂仁县| 广宗县| 且末县| 隆安县| 青田县| 天镇县| 华坪县| 周口市| 出国| 南城县| 中方县| 兴宁市| 麦盖提县| 延川县| 互助| 巧家县| 剑川县| 隆回县| 鄢陵县| 托克逊县| 砚山县| 尤溪县| 密云县| 宜兴市| 库伦旗| 武平县| 浙江省|