Milestone for CNNC at nuclear plant in Pakistan

By Zheng Xin | China Daily | Updated: 2019-06-19 09:24
Share
Share - WeChat
A technician works on the Hualong One reactor at the Fangchenggang nuclear power plant in the Guangxi Zhuang autonomous region. [Photo by Liang Fuying/For China Daily]

The outer containment dome of the Karachi unit 2 nuclear reactor in Pakistan was successfully installed on Monday, a milestone marking the end of its general construction work, said China National Nuclear Corp, one of the country's largest nuclear power companies.

The installation of the outer containment dome of Karachi unit 2, the first export of China's Hualong One pressurized water reactor design, a domestically developed third-generation reactor design, will be followed up by containment and heat tests, it said.

CNNC has four HPR1000 units under construction around the world, which is the world's only third-generation pressurized water reactor nuclear power project constructed according to schedule.

Analysts said the successful installation of the outer containment dome will speed up nuclear cooperation between China and countries and regions participating in the Belt and Road Initiative, boosting confidence in China's Hualong One technology.

After years of development, China has risen from a nuclear energy novice to being a world leader in nuclear plant development globally, said Joseph Jacobelli, an independent energy analyst and Asia-Pacific CEO of clean energy producer Joule Power.

"I believe the nation's nuclear power technology companies should become major suppliers on the global stage as they develop the technologies rapidly, yet cautiously," he said.

"The massive amount of new capacity to be added in China over the next two decades will give them even more scope to test out their technologies. It is not a question as to whether they will join the top global ranks but more when they will do so."

Construction of Karachi unit 2 started in 2015 and is scheduled for commercial operation in 2020, said the company.

According to CNNC, the country's self-developed third-generation nuclear power technology adopts a double containment design, with the outer containment providing protection for the primary containment.

The outer containment dome is a 366-metric-ton multi-surface shell made up of 63 prescribed components.

Unit 5 of CNNC's Fuqing nuclear power plant, the nation's first demonstration nuclear power project using Hualong One technology, has recently succeeded in inverse power transmission, laying a solid foundation for future fuel loading, power generation and transmission for the unit.

China has charted plans to raise its total installed nuclear capacity to 58 gigawatts by 2020, while it also aims to have another 30 gigawatts under construction by the end of 2020.

Top
BACK TO THE TOP
English
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
CLOSE
 
主站蜘蛛池模板: 梁河县| 礼泉县| 奇台县| 桂东县| 民乐县| 乾安县| 阿荣旗| 武川县| 息烽县| 沙田区| 壤塘县| 昔阳县| 清涧县| 临沧市| 东光县| 思茅市| 布拖县| 桦南县| 万宁市| 龙南县| 淳化县| 蕲春县| 阿瓦提县| 马龙县| 丰台区| 疏勒县| 玉山县| 普洱| 许昌县| 马公市| 青阳县| 遂平县| 云安县| 盈江县| 香港 | 余江县| 晴隆县| 丁青县| 鹿泉市| 麻江县| 衡东县| 饶河县| 连云港市| 左权县| 郎溪县| 洞头县| 吉林省| 石景山区| 运城市| 海淀区| 海宁市| 营山县| 安泽县| 阿克| 连州市| 云霄县| 沾益县| 鄂托克旗| 元朗区| 齐河县| 乌兰县| 长宁区| 孝感市| 靖边县| 平安县| 容城县| 旬阳县| 泾源县| 禄劝| 天峻县| 宾阳县| 洪泽县| 阜平县| 台山市| 郸城县| 马龙县| 浏阳市| 赞皇县| 响水县| 突泉县| 南京市| 孟村|