Energy

China's 1st carbon capture plant to start operation by year-end

(Xinhua)
Updated: 2010-06-02 18:18
Large Medium Small

HOHHOT: China's first commercial carbon capture and storage plant is expected to be operational by the end of the year as construction of the plant's liquidification facility has started, company managers said Wednesday.

The environmentally-friendly plant is being built by Shenhua Group - China's top coal producer - in Ordos city on the steppes of northern China's Inner Mongolia autonomous region.

The 210 million yuan ($30.8 million) project is expected to capture 100,000 tons of carbon dioxide every year, Wang Heming, a senior manager in Shenhua Group's Ordos division, said.

China heavily relies on coal to sustain its economy, the world's third largest. But authorities have pledged to slash the carbon intensity of its gross domestic product by 40 to 45 percent from 2005 to 2020. Carbon capture technology has been identified as key to reaching the goal.

Wang said Shenhua is also conducting a feasibility study into a second liquidification facility that will be capable of handling 1 million tons of carbon dioxide annually.

Special Coverage:
Reforming our mode of growth
Related readings:
China's 1st carbon capture plant to start operation by year-end China builds model low-carbon city in Xinjiang's Turpan 
China's 1st carbon capture plant to start operation by year-end Low carbon, New energy, Sustainable development
China's 1st carbon capture plant to start operation by year-end China tries to keep Expo opening gala low-carbon
He said a third - and much larger - facility capable of handling 3 million tons annually is being planned. But no timetable for its construction has been set.

Wang said tests show Shenhua's liquidification facilities pose no harm to the environment, with carbon dioxide being compressed, liquefied and pumped into rocks about 1,000 - 3,000 meters beneath the earth's surface.

A surveillance network will be set up to monitor leaks, Wang said, adding that the storage facility "is tested not to leak for 1,000 years."

But he said the commercial viability of the project is not yet clear.

Standards for the carbon capture industry internationally have not yet been set, and the Chinese government has yet to give companies in the industry favorable treatment, Wang explained.

He said the operating costs of the 100,000-ton facility are estimated at around $50 per ton.

主站蜘蛛池模板: 霍城县| 施秉县| 廊坊市| 都匀市| 游戏| 天全县| 镇康县| 青田县| 静宁县| 商城县| 景洪市| 郎溪县| 资兴市| 海安县| 富锦市| 阜平县| 曲阳县| 澄迈县| 汕尾市| 湘乡市| 乌拉特后旗| 无为县| 孝义市| 皮山县| 开平市| 偏关县| 顺义区| 若羌县| 宁城县| 兴和县| 安阳市| 壤塘县| 贵定县| 奎屯市| 抚州市| 建阳市| 乌审旗| 公安县| 绥宁县| 会昌县| 安乡县| 大余县| 孟州市| 慈利县| 宁远县| 陇西县| 静海县| 东宁县| 迁西县| 平陆县| 乐都县| 普格县| 金寨县| 科尔| 磴口县| 英德市| 文安县| 六安市| 盐源县| 林芝县| 从江县| 富蕴县| 榆社县| 梅河口市| 阳江市| 阳山县| 安陆市| 临沭县| 台南市| 纳雍县| 大连市| 神农架林区| 错那县| 宁河县| 雅江县| 石屏县| 洪洞县| 延吉市| 永丰县| 固镇县| 中阳县| 合阳县|