China's largest direct-drive wind turbine passes critical grid test

(Xinhua)
Updated: 2011-03-18 16:05
Large Medium Small

BEIJING - China's largest direct-drive wind turbine recently passed a critical international test on its capacity to withstand power dips in the national grid, announced the Sino-German maker Friday.

The 2.5 mW direct-drive permanent magnetic wind turbine, independently developed by Guangxi Yinhe Avantis Wind Power Co Ltd (GYAW), recently passed a low-voltage ride through (LVRT) test, said Lars Andreasen, general manager of the turbine maker in Beijing.

"This is so far the largest direct-drive permanent magnetic wind turbine passing the LVRT test in the world," said Lars.

The test measures the capacity of a turbine to maintain continuous online operations when the voltage of the grid dips.

The GYAW wind turbine was connected to the national grid for a trial operation in June 2009, making it the first grid-connected 2.5mW wind turbine in China.

On March 5 this year, the turbine, located on a testing site in Beihai, south China's Guangxi, successfully passed two-phase and three-phase LVRT tests, carried out by China Electric Power Research Institute (CEPRI).

On March 7, the prototype successfully passed the LVRT test based on the International Electrotechnical Commission (IEC) standard.

Few of China's popular 1.5mW wind turbines have passed the test.

In October 2010, a 5mW direct-drive wind turbine rolled off the production line of Xingtan Electric Manufacturing Corporation (XEMC), a wind turbine maker in central China's Hunan.

The turbine is so far the largest in the country, but XEMC is planning to develop 6mW and 7.5mW direct-drive wind turbines.

In March 2010, the National Energy Bureau (NEB) announced it had established a technical committee of wind energy industry standardization to draft the Standard for Wind Power Grid Connection.

At present, the main components of the national standard have been made ready and submitted to the central government for examination.

"Compared with the current technical rules for connecting wind farms to the State Grid, the national standard concerning the LVRT test is stricter, adding requirements for response time and duration of reactive compensation under three-phase short-circuit of wind farm," said, Amanda Yang, an engineer with GYAW.

Chinese wind farm operators have been perplexed and disappointed with the quality of wind turbines.

According to Dai Huizhu, a professor with CEPRI, 598 wind turbines were disconnected from the grid during voltage sags in February this year in Jiuquan, northwest China's Gansu province. Hundreds of turbines met the same problem in January in northeast Jilin province.

Xie Wenbo, from the wind power branch of China Guangdong Nuclear Power Group, said "The 1.5mW wind turbines could operate soundly only for three years. After that, they will show problems one way or the other."

"As a wind farm operator, we are most concerned with the rate of return on investment," said Xie.

Liu Bin from China Wind Power, a leading wind farm developer, said "With wind turbines of the present quality, China cannot realize its ambitious installed capacity objective in 2020."

Related readings:
China's largest direct-drive wind turbine passes critical grid test Go slow for nuclear power projects
China's largest direct-drive wind turbine passes critical grid test Goldwind aims to blow away competition
China's largest direct-drive wind turbine passes critical grid test Non-fossil fuels to take up 11.4% of China's energy use
China's largest direct-drive wind turbine passes critical grid test Wind farm of 49.5 mW connected to grid in Tianjin

To upgrade the existing thousands of wind turbines in operation, mostly without the LVRT function, a huge amount of money will be needed, perhaps up to 1 percent of the value of the turbines, industry officials say.

China aims to have 290 gW of power generation capacity from new energy sources in 2020. Wind power will amount to 150gW and nuclear power 70 gW in installed capacity.

By the end of 2010, China had 44.7gW cumulative wind power installed capacity, replacing the United States to be the largest in the world.

Following explosions at a Japanese nuclear power plant wreaked by the March 11 earthquake and tsunami, the Chinese government announced on March 16 that it had suspended the approval process for the country's nuclear power stations, including pre-construction works of all new nuclear power plants, so that safety standards could be revised.

"Wind power will play an even greater role now in achieving the government's 2020 objectives," said Li Junfeng, deputy director of the energy research institute under the National Development and Reform Commission.

分享按鈕
主站蜘蛛池模板: 阿拉尔市| 芮城县| 老河口市| 博湖县| 长宁区| 庆安县| 日照市| 东乌珠穆沁旗| 呼图壁县| 青铜峡市| 土默特左旗| 涟源市| 罗源县| 洪泽县| 刚察县| 武穴市| 延寿县| 霍林郭勒市| 隆昌县| 彭阳县| 博兴县| 宜春市| 静乐县| 塘沽区| 和静县| 庆城县| 怀化市| 杭州市| 青神县| 广灵县| 布拖县| 沁水县| 沅江市| 成安县| 双辽市| 灵山县| 屏山县| 射洪县| 文山县| 郁南县| 博罗县| 肥城市| 香港 | 西昌市| 横山县| 雷山县| 中超| 张家界市| 浦江县| 梁平县| 和田县| 贡山| 米泉市| 龙门县| 常德市| 黄梅县| 遂溪县| 大石桥市| 仁布县| 梅州市| 滦平县| 琼中| 昭觉县| 诏安县| 新平| 荆门市| 新干县| 新乡县| 旬阳县| 静海县| 柏乡县| 山丹县| 宁夏| 连山| 互助| 和田市| 赤壁市| 华容县| 泰安市| 米泉市| 黄山市| 景泰县|