Boeing to deliver B787s to Chinese airlines on time

By Lu Haoting (China Daily)
Updated: 2007-09-11 09:21

Boeing is still aiming to deliver its B787 Dreamliner to Chinese airlines on time before the 2008 Summer Olympic Games despite delays in the aircraft's first flight, the US aerospace group said yesterday.

"There is no change in our delivery schedule and the five Chinese airlines will receive their first B787 before the Olympic Games," said an official from Boeing China's communications department.

Boeing has received 60 orders from five Chinese airlines - Air China, China Eastern Airlines, China Southern Airlines, Hainan Airlines and Shanghai Airlines.

The first flight of the B787 will be delayed by two more months as Boeing struggles to overcome problems in final assembly and completing the flight control software, the Seattle-based company said last Thursday.

The B787's maiden flight was originally planned for August and was postponed to late September. But now it has been delayed to between mid-November and mid-December, said Mike Bair, Boeing vice-president and general manager of the B787 program.

But despite the setback, Boeing aims to deliver the first of the new long-haul jets to Japan's All Nippon Airways on time next May, Bair said.

Boeing previously said the bulk of the subsequent deliveries for several months would all go to Chinese airlines.

If Boeing is to meet that target, the delays in the first flight mean the certification trials would have to be finished in about five months.

It usually takes one to two years for a new aircraft to complete certification trials before entering commercial service. Airbus spent a year and a half completing the flight test campaign of its latest model, the A380.

"We haven't got any information regarding delays in the delivery of our first B787," said Rao Xinyu, board secretary of Air China Ltd. The nation's flagship carrier has ordered 15 B787 jets.

Air China is scheduled to receive two B787 jets next year, with one delivered next June, Rao said. The aircraft will most likely be used on the airline's routes to Europe or the US, Rao added.

A major problem delaying the B787's first flight is the amount of unfinished structural work passed on to the Boeing final assembly plant at Everet, near Seattle, from suppliers with incomplete documentation, the Financial Times has reported.


(For more biz stories, please visit Industry Updates)



Related Stories  
主站蜘蛛池模板: 庆城县| 天津市| 大埔区| 共和县| 廊坊市| 吴堡县| 海口市| 时尚| 万安县| 社会| 廉江市| 墨玉县| 灯塔市| 资阳市| 平远县| 武城县| 南昌县| 齐河县| 洪泽县| 交口县| 北票市| 象州县| 扎兰屯市| 那坡县| 温泉县| 大理市| 天峻县| 伊宁市| 屏东市| 安丘市| 云浮市| 星子县| 无棣县| 吴忠市| 广汉市| 顺义区| 醴陵市| 汤原县| 建始县| 平昌县| 盘锦市| 邳州市| 辽宁省| 武宁县| 波密县| 凯里市| 甘南县| 卢龙县| 文登市| 屏边| 龙南县| 镇原县| 宁都县| 沙坪坝区| 台湾省| 维西| 建湖县| 泽州县| 株洲市| 刚察县| 鸡西市| 旬邑县| 巴彦淖尔市| 乌拉特前旗| 东乡| 岑溪市| 和平区| 永平县| 兴安盟| 乡城县| 大荔县| 互助| 将乐县| 桃园市| 太湖县| 安化县| 益阳市| 永泰县| 甘肃省| 镇远县| 玉环县| 巴彦淖尔市|