Extra-high-voltage line construction 'needs speeding up'

By Du Juan | China Daily | Updated: 2013-05-07 10:15

China should accelerate construction of an extra-high-voltage transmission line to deliver power generated by new energy, according to a senior official.

"The so-called overcapacity problem of China's new-energy industry does not refer to energy, but the equipment for new-energy production," said Zhang Guobao, former director of the National Energy Administration under the National Development and Reform Commission, during an interview with Xinhua News Agency.

He said domestic new-energy equipment manufacturing companies have met difficulties in exporting their products, which has resulted in overcapacity in the domestic market, but China's new-energy operators are "doing fine".

"China's new-energy industry is highly market-oriented with a significant number of private companies, which make decisions based on their abilities to take risks," he said. "The government is considering calling off some governmental approval processes to help companies reduce costs."

In the past year, non-fossil power generation output reached 1.07 trillion kWh, accounting for 21.4 percent of the country's total. The major contributor is still hydropower, which reached 800 billion kWh, Zhang said.

Although wind power has developed rapidly in China, with total output reaching 100.4 billion kWh in the past year, it still comprises only 2 percent of the country's total output.

In recent years, many power groups have built wind farms and produced wind turbines. However, the use of wind farms is low due to sluggish construction of electricity transmission lines.

China's northern areas are rich in wind resources, and wind power generation accounts for up to 20 percent of power consumption in some regions.

However, because of the shortage of transmission lines, a huge amount of wind power cannot be delivered to other provinces, resulting in a severe waste of wind power.

Zhang said China wasted about 20 billion kWh of power in 2012.

He suggests the government accelerate approval for an extra-high-voltage transmission line connecting Xilinhot in the Inner Mongolia autonomous region to Nanjing in Jiangsu province, a large power consumer in China, and for another line to deliver power from Jiuquan in Gansu to the rest of the country.

Hydropower is facing a similar overcapacity problem, with 10 hydropower stations in southern China going to start production in June.

Liu Zhenya, general manager of State Grid Corp of China, the world's largest utility by revenue, told an industrial conference in April the company will invest more than 3 trillion yuan ($480 billion) in the next eight years to build safe and effective national grids and accelerate building of extra-high-voltage transmission lines.

Most Viewed in 24 Hours
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
主站蜘蛛池模板: 河津市| 延长县| 安平县| 湖州市| 西林县| 象州县| 北宁市| 鸡西市| 英吉沙县| 民乐县| 咸丰县| 富宁县| 苍南县| 临朐县| 金坛市| 平阴县| 洪雅县| 江门市| 合作市| 陈巴尔虎旗| 建德市| 棋牌| 佳木斯市| 洪泽县| 灵璧县| 河津市| 墨脱县| 崇义县| 隆德县| 甘德县| 崇明县| 洛阳市| 怀集县| 武威市| 黄龙县| 夹江县| 遂溪县| 克拉玛依市| 宜川县| 白银市| 咸宁市| 来凤县| 深水埗区| 兴化市| 独山县| 新宾| 昌吉市| 望江县| 大洼县| 泗阳县| 新干县| 威远县| 黄冈市| 长葛市| 台安县| 洛浦县| 兴山县| 南京市| 久治县| 岱山县| 高清| 株洲县| 十堰市| 甘肃省| 翁牛特旗| 丰顺县| 桂阳县| 河南省| 灵寿县| 龙陵县| 弋阳县| 肇州县| 铜陵市| 深水埗区| 五台县| 大英县| 景德镇市| 昂仁县| 乳山市| 普陀区| 桂平市| 岱山县|