China / Society

New Beijing subway to ease traffic congestion

By Zheng Xin (China Daily) Updated: 2012-11-26 07:23

The Beijing subway's Line 6 is scheduled to begin operating by the end of the year after undergoing more than two years' construction, metro authorities said over the weekend.

Passengers will first be able to travel Line 6, which will run from Wuluju in Haidian district in the west of the city to Caofang in Chaoyang district in the east, on Dec 28. Among its many benefits, the new line is expected to alleviate traffic congestion, according to the Line 6 project department of the China Railway Tunnel Group.

"It's believed subway Line 6, with its greater space for passengers and faster speed, will lead to smoother passenger flow during rush hours," said Wu Wenjie, deputy director of the department.

Wu said the line is now being put through various tests.

"We need to make sure everything is working well, from the subway's signal system to the elevators," Wu said. "We can't tolerate any negligence or carelessness, especially in the project's final phase."

The line will connect 20 stations and be able to accommodate 1,960 people in a single run. That's more than can be carried in a single trip on any of the city's current subway lines.

Line 6 will also be the fastest in the city's subway system, capable of reaching a speed of 100 km an hour.

"Subway Line 6 will far exceed the current high speed of 80 km per hour (in the Beijing subway system)," Wu said. "It will only take 48 minutes to travel the whole line, in part because the stations it connects are pretty far apart from each other."

The longest distance between two consecutive stations on the line is 4,001 meters, according to the department.

Beyond capacity and speed, Line 6 will connect to the deepest station in the capital's underground transport system.

The line's connection to the existing Dongsi station, where Line 5 now goes, will lie 34 meters underground, the department said.

Nearly 235 wells have been dug around the station to prevent water from seeping into it. All of them are 142 meters deep and 1 meter in diameter, according to Zhuo Linjian, technical supervisor of the Line 6 project department of the China Railway Tunnel Group.

"The construction team has overcome lots of the difficulties that arise from complicated underground geological conditions," he said.

zhengxin@chinadaily.com.cn

Highlights
Hot Topics

...
主站蜘蛛池模板: 大名县| 临高县| 探索| 旺苍县| 靖宇县| 驻马店市| 读书| 东乌珠穆沁旗| 贺州市| 岚皋县| 四川省| 岳西县| 秦皇岛市| 平山县| 嘉鱼县| 松原市| 乌鲁木齐县| 宜良县| 集安市| 封丘县| 保德县| 浮梁县| 新兴县| 石狮市| 上饶县| 成武县| 商河县| 瓦房店市| 长海县| 安塞县| 成都市| 阿巴嘎旗| 体育| 亳州市| 哈巴河县| 九寨沟县| 长丰县| 武宣县| 遂昌县| 凤山县| 延长县| 灵武市| 留坝县| 丰宁| 尚义县| 新平| 兴和县| 大同市| 三原县| 昆明市| 漠河县| 伊通| 商丘市| 三明市| 贵阳市| 七台河市| 琼结县| 澜沧| 莱州市| 同德县| 阿勒泰市| 阳江市| 无为县| 和平县| 双桥区| 会同县| 武冈市| 莱州市| 喀喇沁旗| 井陉县| 调兵山市| 武威市| 贵德县| 玉树县| 葫芦岛市| 江北区| 辽宁省| 凌云县| 鄂伦春自治旗| 阳春市| 舒兰市| 嘉荫县|