Repairs to delay Capital Airport flights

By Luo Wangshu | China Daily | Updated: 2017-03-23 07:15

The number of flights landing and taking off from Beijing Capital International Airport will be cut by more than 300 a day in April to allow for runway maintenance, officials said on Wednesday.

The world's second busiest airport will close one of its three runways between April 2 and April 29, the officials said. About 40 percent of flights take off or land on this runway every day.

The closure will reduce flights by about 20 percent and passengers by 10 percent to 15 percent, according to Sun Xiaoyi, deputy general manager of the airport's service promotion department.

She said passengers who had booked tickets in advance should check with their airlines about any changes to their flights. Flights could be further delayed by bad weather, Sun said, asking passengers for their understanding.

Repairs to delay Capital Airport flights

"Flights are expected to be full and passengers should arrive at the airport earlier than usual," she said.

Wang Yanling, business manager of the airport's operation control center, said the runway being closed is the middle one of three runways.

"The closure may increase the distance some flights will need to taxi and therefore prolong passengers' time sitting in planes when they take off and land," she said, adding passengers may have to wait about 10 extra minutes. The average taxi time now is 27 minutes before takeoff, she said.

During the maintenance work, the airport will handle 70 flights an hour during rush hours and about 1,430 flights a day. Freight flights also will be affected.

The project covers nearly 200,000 square meters, with a total cost of up to 172 million yuan ($25 million).

The runway, in service since 1958, was the first at the capital's airport. It went through a thorough maintenance construction in 1996 and was shut down again in 2015 for six days.

"The runway was designed for usage for 10 years since 1996 but it has been put in service for more than 20 years," said Chen Long, deputy general manager of the airport's construction projects and management center.

"The maintenance is for safety. The runway is very old and became dilapidated due to heavy traffic. Some areas even have cracks. Gravel from cracks could enter engines, which may cause a severe safety hazard," he said.

Editor's picks
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
 
主站蜘蛛池模板: 正宁县| 浦江县| 宁德市| 两当县| 乃东县| 木兰县| 华宁县| 新泰市| 桑日县| 和田市| 清丰县| 深水埗区| 彝良县| 通化县| 泰和县| 凉城县| 广宁县| 永川市| 突泉县| 明光市| 广元市| 同江市| 和田县| 奉节县| 沁源县| 丰都县| 连城县| 曲水县| 临漳县| 张北县| 抚顺县| 长兴县| 德阳市| 萨嘎县| 正定县| 通渭县| 兴安盟| 陇南市| 贵州省| 周至县| 乌拉特中旗| 洪泽县| 宣恩县| 准格尔旗| 古蔺县| 高淳县| 岱山县| 炉霍县| 凭祥市| 抚宁县| 临澧县| 兴业县| 梅州市| 攀枝花市| 西丰县| 襄垣县| 花莲市| 闵行区| 曲松县| 天柱县| 广河县| 通海县| 正镶白旗| 铜鼓县| 资阳市| 汶川县| 玉林市| 德庆县| 江孜县| 高要市| 常山县| 忻州市| 玉溪市| 白城市| 湄潭县| 蒙自县| 麻城市| 永靖县| 怀来县| 赤城县| 常熟市| 孝昌县|