US to BP: devise better leak response in 48 hours

(Agencies)
Updated: 2010-06-13 09:07
Large Medium Small

BOSTON - A top US Coast Guard official has told BP Plc the company's plans to contain the gushing oil spill in the Gulf of Mexico do not go far enough or contain enough back-up measures.

US to BP: devise better leak response in 48 hours
Bridget Hood, 14, of Bay Minette, Alabama (L) and Emily Davis, 23, of Gulf Shores, Alabama hold a sign demanding action in the wake of the BP oil spill as they gather with other protesters under the Perdido Pass bridge in Orange Beach, Alabama June 12, 2010. [Agencies]?

"BP must identify in the next 48 hours additional leak containment capacity that could be operationalized and expedited," Coast Guard Rear Admiral James Watson said in a letter to BP dated June 11.

Related readings:
US to BP: devise better leak response in 48 hours Spill oil to seep into supply chain as BP sells it
US to BP: devise better leak response in 48 hours US doubles estimate of oil flow
US to BP: devise better leak response in 48 hours US House slams BP over dividend as estimate for oil spill up
US to BP: devise better leak response in 48 hours Gulf oil leak may be bigger than BP says

Watson, the federal on-scene coordinator for spill response, noted estimates of the amount of oil leaking from BP's damaged well have been raised sharply.

He did not suggest what actions could be taken if the 48-hour deadline was not met.

Watson's letter was a response to one from BP that described the company's multi-phase plans to contain the spill, involving several elements to be phased in by mid-July.

"The combination of Phase One and Two results in a capacity of 40,000 to 50,000 barrels of oil per day," said Doug Suttles, BP's chief operating officer.

"We believe this plan is responsive to your order," Suttles said, adding the company cannot assure that "complete collection rates" are guaranteed.

Not good enough, said Watson.

"You indicate that some of the systems you have planned to deploy may take a month or more to bring online. Recognizing the complexity of this challenge, every effort must be expended to speed up the process," he wrote.

"I am also concerned that your plan does not go far enough to mobilize redundant resources in the event of an equipment failure with one of the vessels, or some other unforeseen problem."

主站蜘蛛池模板: 镇远县| 理塘县| 昌平区| 千阳县| 东明县| 府谷县| 志丹县| 奉贤区| 许昌市| 天台县| 县级市| 陆良县| 汉寿县| 石城县| 洛阳市| 福建省| 嘉善县| 阿图什市| 永州市| 莱西市| 毕节市| 林芝县| 夏河县| 当雄县| 西平县| 射阳县| 化隆| 贵州省| 黎川县| 北京市| 汉寿县| 大埔区| 赣榆县| 珠海市| 正蓝旗| 邓州市| 湖北省| 遂宁市| 辛集市| 托克逊县| 惠来县| 雅江县| 宁津县| 石狮市| 兰溪市| 阆中市| 珲春市| 罗甸县| 鸡西市| 温宿县| 玉山县| 靖宇县| 定州市| 抚顺市| 广汉市| 宜都市| 嘉义市| 迁安市| 金塔县| 鄱阳县| 南皮县| 崇文区| 邢台县| 揭西县| 乌苏市| 惠安县| 镇江市| 凤山县| 西吉县| 博野县| 射阳县| 额敏县| 新乡市| 荃湾区| 邓州市| 任丘市| 大新县| 龙游县| 寿宁县| 旺苍县| 南溪县| 武川县|