Medical facilities reflect mainland engineering efficiency

By Su Zihan in Hong Kong | chinadaily.com.cn | Updated: 2021-10-28 12:36
Share
Share - WeChat
This photo shows a view of the Specimen Reception Counter at the North Lantau Hospital Hong Kong Infection Control Centre on Oct 27, 2021. [Photo by EDMOND TANG / CHINA DAILY]

Editor's notes: In a Tuesday lecture, Zhang Yi, CEO of China State Construction International Medical Industry Development Corp, shared with Hong Kong students the stories behind the construction of two Hong Kong medical facilities built with the nation's help to combat the COVID-19 pandemic.

Here are the profiles of the two projects and some impressive figures from Zhang's speech.

North Lantau Hospital Hong Kong Infection Control Centre

Started operation on Feb 26, 2020

Building area: 44,000 square meters

Floor space: 29,000 square meters

Facilities: 6 ward buildings, 1 medical center building, 1 energy center building, 1 liquid oxygen station, 1 dangerous-goods warehouse and some other ancillary facilities

Beds: 816 negative-pressure isolation beds

Service life: Permanent building

Community treatment facilities at AsiaWorld-Expo

China's first high-standard intelligent negative-pressure mobile cabin hospital

Started operation on Aug 1, 2020

Building area: 30,000 square meters

Facilities: 40 negative pressure isolation wards with a total of 160 beds

792 beds in general square cabins

32 communal facilities, including nurses stations

Provision of additional air-conditioning facilities

Beds: 952

Efficiency and safeguards of the two projects

-Finished 21 versions of designs in 7 days

-Shortened the construction period of the temporary hospital from 3 to 4 years to 4 months

-Cumulative number of workers on site exceeds 240,000, with over 4,000 workers worked on-site a day at the peak of the construction

-Over 200 subcontractors and 130 suppliers in Hong Kong served as a backup team

-Procured materials and equipment from nearly 20 countries or regions around the world. The transportation volume reached the loads of more than 40,000 trucks.

Top
BACK TO THE TOP
English
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
 
主站蜘蛛池模板: 柳江县| 白城市| 巴中市| 区。| 绥化市| 沂水县| 金阳县| 常德市| 云和县| 顺平县| 泗阳县| 广州市| 承德市| 将乐县| 宿松县| 将乐县| 苏尼特左旗| 广平县| 邯郸市| 准格尔旗| 房山区| 潼南县| 泗洪县| 宁河县| 会理县| 阳山县| 延吉市| 塔城市| 韶山市| 岑溪市| 嘉荫县| 昌邑市| 福海县| 长泰县| 永丰县| 杭州市| 博野县| 抚顺县| 贡山| 太白县| 喀喇| 库尔勒市| 凤冈县| 榆中县| 金湖县| 台东市| 云安县| 报价| 卫辉市| 罗田县| 公主岭市| 响水县| 勐海县| 临沧市| 孟连| 邯郸市| 正宁县| 大化| 富蕴县| 拉萨市| 都兰县| 阳山县| 霍山县| 汉沽区| 稻城县| 西华县| 交城县| 册亨县| 白城市| 斗六市| 宿州市| 焦作市| 莱州市| 治多县| 金华市| 广安市| 贵州省| 永州市| 五华县| 大洼县| 城市| 荣昌县|