Huaneng seeks larger presence

The central control room of Huaneng Group in the port economic zone of Tianjin municipality. The power giant said it plans to install capacity of nuclear power amounting to 1.45 million kilowatts by 2015.[Photo/China Daily]

Energy giant puts 'great effort into inland nuclear power projects'

CHENGDU - The power giant Huaneng Group said it has ambitious targets to achieve an installed capacity of 1.45 million kilowatts (kW) of nuclear power by 2015 and 7.7 million kW by 2020.

"We are a latecomer to the nuclear power sector, but we are taking gradual and solid steps to boost our presence in the area," said Cui Shaozhang, deputy general-manager of Huaneng Nuclear Power Development Co Ltd at the China (Chengdu) New Energy International Summit 2011.

Since nuclear accidents at Japan's Fukushima Nuclear Power Plant in March, Chinese companies have been taking added precautions in their nuclear development to ensure safety.

Huaneng now ranks as second globally and No 1 in Asia in terms of general power generation.

By January, the total installed power capacity of its 175 power plants, coal and new energy, hit 118 million kW. Its installed capacity and power generation account for more than 10 percent of the China's total.

"We are now devoting great effort to inland nuclear power projects," Cui said. "It's an inevitable choice, because the lion's share, or let's say, most of the best locations for offshore projects have been snatched by leading counterparts, and inland power projects are cost-efficient," he said.

Huaneng has made most of its investments in high temperature gas cooled reactors, which have a higher safety level and the best emission treatment facilities.

It has launched a project with the technology in Shidaogang port, in eastern Shandong province, with current installed capacity of 200,000 kW - Cui declined to disclose the amount of the investment.

The company has a current installed capacity of 500,000 kW in nuclear projects it owns independently and a combined installed capacity of 640,000 kW of nuclear power it operates for other companies.

Also at the forum was an executive with China Power Investment Corp, who said the company expects the installed capacity of its nuclear projects to account for 15 percent of its total power by 2020.

According to Hao Hongsheng, president of the Jiangxi Branch of the China Power Investment Corp, the company has been investing in a project in Pengze, in northeastern Jiangxi province, since 2008.

The investment is expected to reach 2.9 billion yuan ($453 million), and Hao said the province has high hopes for the power the plant will generate.

Cui said that inland nuclear plants have become the major trend in China.

There are 27 projects now under construction in China, with planned installed capacity of 3.75 million kW.

"Inland plants represent the major development prospect for the sector globally, while the key challenges are emission treatment and natural disasters," Hao said.

Peng Chao contributed to this story.

主站蜘蛛池模板: 沙坪坝区| 乐山市| 尤溪县| 庆元县| 华宁县| 大理市| 大渡口区| 金溪县| 斗六市| 浠水县| 山阳县| 青州市| 安宁市| 西吉县| 邹城市| 奈曼旗| 鹿邑县| 南通市| 滨海县| 陵川县| 杂多县| 兴业县| 仙居县| 太保市| 开江县| 象山县| 清涧县| 微山县| 合水县| 和顺县| 肥西县| 玛曲县| 南汇区| 微山县| 永春县| 临江市| 巴林左旗| 赤峰市| 彝良县| 宽城| 沧州市| 鲜城| 平阳县| 琼中| 辽源市| 苍溪县| 临江市| 威远县| 绥江县| 通河县| 喀什市| 金山区| 泸水县| 周宁县| 兴国县| 临湘市| 惠州市| 兴山县| 东丰县| 神木县| 调兵山市| 安吉县| 汾阳市| 麟游县| 咸丰县| 柞水县| 五大连池市| 华宁县| 满城县| 砀山县| 烟台市| 荆门市| 内乡县| 钟山县| 洛浦县| 安岳县| 新泰市| 绥化市| 定西市| 海林市| 高雄市| 九寨沟县|