Maiden flight in holding pattern

Updated: 2013-08-07 01:20
By Wang Wen and Zhao Lei ( China Daily)

Manufacturer pushes introduction of C919 large jetliner back one year

China's dream of having its first large commercial jetliner may have hit some turbulence, as the maiden test flight of the C919 will be delayed by a year to 2015.

Zhang Yanzhong, director of the program's advisory committee of experts and a member of the Chinese Academy of Engineering, said the program encountered difficulties due to the manufacturer's present level of technological expertise and experience building commercial aircraft, but that these are not major setbacks.

"Generally speaking, the project is going well now," he said on Tuesday, without elaborating on what the issues are.

Based on the project's progress, it is impossible to make the maiden test flight in 2014 as planned, said an official with the Commercial Aircraft Corp of China, builder of the C919.

The first delivery of the C919, planned for 2016, may also be delayed, said the official, who is familiar with the project but declined to be identified.

Wang Ya'nan, deputy editor-in-chief of Aerospace Knowledge magazine, said it will take at least two to three years for domestic and foreign authorities to authenticate the airworthiness of the C919.

"The earliest time for its delivery to buyers is likely to be in 2018 or 2019," Wang said.

Chinese airlines that placed orders for the jetliners said they will patiently wait for delivery.

"Only one year delay is OK for us, as it will not have much adverse effect on the airline's operations," said an official from a domestic airline who did not want to be named.

By the end of 2012, at least 15 companies, most of them Chinese, agreed to buy 380 of the aircraft.

GE's aircraft leasing arm has signed on to take 20 of the C919 planes. Other customers include China's big three airlines — Air China, China Southern Airlines and China Eastern Airlines — and the leasing units of lenders such as Bank of China, Industrial and Commercial Bank of China, and Bank of Communications.

Material and component suppliers of the aircraft have not been informed about the schedule changes.

"We are still working on the projects in line with the original schedule," said Xu Yingbing, director of communications (Asia-Pacific) of Honeywell Aerospace.

Honeywell Aerospace provides major systems including guidance systems and auxiliary power units for the C919.

Honeywell International and CFM International, a venture between General Electric and Safran SA, are among the C919's major suppliers.

The program's delay is not a total surprise, experts said.

"I think the maiden flight of the C919 will be conducted in 2015, and it is quite natural that the date of the test flight is postponed," Wang said.

Development and testing of a new aircraft, especially a large jetliner, go through very complicated processes, he said, noting that companies like Boeing and Airbus had also delayed test flights.

Some of the postponements of Boeing and Airbus were caused by technical problems, but sometimes they were made out of commercial considerations, Wang said.

For instance, the company knew that it would take five years to develop a new aircraft but still announced that the maiden flight would be performed within four, Wang said.

"The reason they deliberately announced an early date was to grab the market," he said.

China is building the 168-seat plane as it tries to break the stranglehold of Airbus SAS and Boeing in the global market for aircraft of this size. Last year, COMAC, builder of the C919, asked its project designers to work 12-hour days and six-day weeks to meet the deadline for the maiden flight.

The C919 is not China's first attempt to build a large plane. From the early 1970s to the mid-1980s, China worked on the four-engine, narrow-body Y-10, but the project was eventually aborted after doubts over the aircraft's profitability and feasibility, although three prototypes had been manufactured.

"The C919 is hence the first, so it is logical that China may take a longer time to develop it," Wang said.

The biggest obstacle developers have to overcome is the propulsion system, he said.

"In addition, whether the test flight can be performed on schedule depends on the results of ground tests, which examine the performance of every system on the plane."

COMAC has started the parts and components manufacturing of C919, and it is working on the research of some key technologies, according to the company.

Contact the writers at wangwen@chinadaily.com.cn and zhaolei@chinadaily.com.cn

Bloomberg contributed to this story.

 
...
...
...
主站蜘蛛池模板: 藁城市| 新津县| 太原市| 富蕴县| 平舆县| 新兴县| 黎平县| 司法| 满城县| 柯坪县| 灵寿县| 南丹县| 安陆市| 浪卡子县| 金乡县| 英山县| 永善县| 邳州市| 桃源县| 福贡县| 元谋县| 思南县| 金昌市| 沅江市| 丰镇市| 通辽市| 砚山县| 读书| 桦川县| 修武县| 乡宁县| 祁阳县| 庆阳市| 武强县| 襄樊市| 临高县| 安陆市| 金湖县| 江城| 湘阴县| 库车县| 邻水| 清镇市| 云龙县| 大安市| 永平县| 叙永县| 宝坻区| 吉水县| 万宁市| 会宁县| 安义县| 常宁市| 蒙自县| 灵武市| 麻城市| 新丰县| 桐乡市| 栖霞市| 德安县| 玉山县| 连城县| 基隆市| 信宜市| 敦化市| 雷山县| 石景山区| 合川市| 济源市| 枣阳市| 资阳市| 哈巴河县| 田阳县| 荔浦县| 枞阳县| 鞍山市| 綦江县| 苏尼特左旗| 屯昌县| 卢龙县| 屏山县| 神农架林区|